NEWS / Infrastructure Intelligence / HS2 tunnelling to Euston reaches halfway point

Image: HS2

24 NOV 2026

HS2 TUNNELLING TO EUSTON REACHES HALFWAY POINT

Construction of HS2’s final deep-bored tunnel into central London has passed the halfway point, with the route 4.5 mile tunnel to Euton due to be completed next year.

Tunnel boring machines (TBMs), named Karen and Madeleine, have now excavated around 2.25 miles of the Euston Tunnel, which will connect Old Oak Common with the new HS2 station at Euston.

The 1,624-tonne machines were launched from Old Oak Common in January and March this year and have advanced at a rate of around 16 metres a day. By mid-November, both TBMs had reached the area between West Hampstead and Kilburn High Road stations as they continue their journey beneath the capital.

The tunnel is being delivered by Skanska Costain STRABAG joint venture (SCS JV), HS2 London tunnelling contractor with the machines operating around the clock.

HS2 chief executive Mark Wild said: “Reaching the halfway mark for building the programme’s last deep bored tunnel is a magnificent achievement by everyone involved. Their work driving the high speed line into central London is fundamental to the long term ambition of increasing the prosperity of the area around Euston. I wish everyone a safe journey to their final destination.

“HS2 Ltd is now in the last phases of a root and branch full-programme reset that will safely deliver the railway at lowest reasonable cost.  The new line we’re driving to Euston will complement the existing station and the West Coast Mainline, providing fast and reliable long distance journeys with its new capacity.”

The tunnelling programme is expected to generate around 1.5 million tonnes of excavated material. As work progresses, the TBMs are installing 48,294 concrete tunnel lining segments manufactured in Hartlepool.

The TBMs will finish underground on the approach to Euston. Once stopped, key elements of the machine will be pulled back through the tunnel. The cutterhead, spanning 8.53-metres will be excavated from the Euston Cavern and removed. The outer part of the front of the machine, known as the shield or ‘can’, will remain underground and will be grouted in behind the concrete tunnel lining.

 