NEWS / Infrastructure Intelligence / First of 500km of cables being laid at Hornsea 3

Array cable vessel
Image: Flying Focus

18 NOV 2026

FIRST OF 500KM OF CABLES BEING LAID AT HORNSEA 3

Installation of the first of more than 500km of array cables is now underway at the Hornsea 3 Offshore Wind Farm site.

Array cables are underwater power lines that will link the project’s 197 offshore wind turbines to Hornsea 3’s two offshore converter stations so that they can transport power back to shore.  They are buried up to 70m below sea level at the site in the southern North Sea.

These are an essential part of Hornsea 3, an £8.5bn infrastructure project that will generate 2.9 GW of renewable energy – enough to power more than 3.3 million UK homes. 

The installation marks the culmination of five years of work for Ørsted’s Hornsea 3 array cable team. Works have been going on throughout that time, including the manufacture of the array cables by suppliers Hellenic and Prysmian, mapping the seabed and the clearance of more than 2,300 boulders from the cable route.

Carried out by Seaway7, the array cable installation is a key milestone on Hornsea 3 as these will transport power generated by the wind turbines to the offshore converter stations before it is then taken back to shore.

Luke Bridgman, managing director of Hornsea 3 at Ørsted, said:  “After almost five years of hard work we’ve reached the key moment for our array cables. The installation programme is a significant milestone that underpins the construction of Hornsea 3 Offshore Wind Farm.

 “Seeing everything come together is what the whole team, both those at Ørsted and our suppliers, have been looking forward to. They have shown true grit and perseverance to ensure that we have successfully arrived at this point.”

Once installed, the cables are connected, tested to confirm they are working safely and correctly, and prepared for energisation, with the whole process taking just over a year. 

 