Three major projects which will help boost the country’s energy security, clean power ambitions and deliver projected savings for consumers have taken a major step forward.
Ofgem said it had approved updated delivery dates and early investment for three major electricity ‘superhighways’.
It said bringing forward the projects is expected to deliver a £3-6bn benefit to consumers compared to the original network design primarily due to the earlier achievable delivery dates and avoided network constraint costs.
The projects are Eastern Green Link 3 (EGL3) and Eastern Green Link 4 (EGL4) which are two proposed subsea cables which would each provide 2GW of capacity to transport electricity generated from British offshore wind between Scotland and England via a network of onshore and offshore cables.
Another proposed project, GWNC, plans a new onshore 400Kv electricity link between Grimsby and Walpole in Lincolnshire, to help transport the energy to consumers
The proposed projects involve building high-capacity, electricity transmission links that would enable consumers to access more homegrown clean power, with the additional capacity provided by the links also reducing payments made to windfarms to switch off, when there’s no capacity to transport their energy on the grid.
Ofgem has approved amendments to the scope of the projects, including forecast costs and later target delivery dates, after transmission operators (TOs) proposed major design changes to reduce the impact of the projects on the local environment and ensure additional renewable generation could also be connected.
New target dates of December 2033 for GWNC and August 2034 for EGL3 and EGL4 have now been set.
Ofgem has also approved early construction and preconstruction funding (ECF and PCF) for EGL3 and EGL4, which will enable for the projects to proceed with enabling works such as strategic land purchases, surveys, design work and procurement of sought after components, equipment and materials.
Beatrice Filkin, Ofgem director of major projects, said: “Today’s decision puts these projects in a prime position to compete in the global race for sought after components such as HVDC cables and work towards seeking planning approval.
“We’re neither handing TOs blank cheques nor greenlighting the projects themselves – that is rightly for the relevant planning authorities to decide. Through intelligent use of early investment and setting realistic but ambitious timescales, we are helping shield consumers from unnecessary costs."
She added: “Our processes help minimise wasted expenditure, if projects are altered, cancelled or refused permission, with any unspent money returned to consumers. The TOs must also demonstrate that their expenditure delivers clear benefits for consumers – otherwise those costs can’t be passed on to billpayers.
"When ASTI (Accelerated Strategic Transmission Investment) was implemented, it was recognised that the design and delivery dates of these projects might change, and our decision today ensures that the TOs face a suitably challenging date by which to deliver the updated design."
ASTI was launched by Ofgem in late 2022, to streamline the delivery of major strategic energy infrastructure projects. It identified 26 projects key to achieving government decarbonisation targets and reducing Britain’s exposure to volatile international gas prices. The projects will enable more homegrown power to be harnessed and supplied to consumers, while also driving down the costs currently incurred when, for example, wind generators are paid to stop generating because there isn’t the grid capacity for their energy.
