Construction of a new overbridge on HS2’s route in the Midlands has reached the halfway mark after 11 months of work.
The new road bridge will enable the high-speed railway to be built under the A45 between Stonebridge Island and Junction 6 of the M42.
A team of engineers working for HS2’s construction partner Balfour Beatty VINCI (BBV), have completed the first section of the new Coventry Road overbridge, near Bickenhill. This structure is being constructed in two halves, to ensure that existing traffic flows along the A45 are maintained, minimising impacts on the local road network.
Completion of the waterproofing and highway works in the coming weeks means the eastbound section of the new structure will soon be brought into use and HS2 is working closely with National Highways to prepare for the upcoming traffic management changes.
From 7 December, a series of overnight and weekend closures will be put in place to facilitate the traffic switchover. Once complete, motorists will begin using the temporary carriageway alignment over the new eastbound section of the bridge.
Paul Marshall, head of delivery at HS2, said: “Our engineers have worked incredibly hard to develop a design solution that maintains traffic flows in each direction, while we build the bridge and excavate the ground below to make way for the new high-speed railway.”
In the new year, BBV’s engineering team will start work on the second section of the bridge, following a similar sequence of works.